Project Substation Belo Monte

7 transformers were transported by barge in two voayges from Santos to Xingu River, which is localizated in Pará state. The approximate distance between origin and destination was 3.000 nautical miles in 27 days.

The first voyage had 4 transformers with 303 tons each one and the second voyage had 3 transformers.